24 factory machines moved from Bekasi to Makassar in 11 days, with zero damage

Client
LOGO PT Contoh Kemasan Nusantara
Service
Project cargo, land and sea
Cargo
24 production machines, 186 tonnes in total
Route
Cikarang, Bekasi → Tanjung Priok → Makassar → KIMA
Duration
11 days · March 2026

Sample case study · data not final

01

Challenge

The client was moving its entire packaging production line from Cikarang to a new plant in the Makassar Industrial Estate. Every day the line stood still, customer orders slipped.

Management set the target: production in Makassar had to restart within 14 days of the first machine being dismantled.

  • Heaviest machine 18 tonnesNeeded a lowbed and a 50-tonne crane at both ends.
  • Precision componentsExcess vibration could throw the calibration off.
  • Limited sailingsOnly two vessels could take flat racks that week.

02

Solution

  1. 1
    Survey and lift plan

    The team measured every machine, its centre of gravity and the access at both plants. The client's engineer approved the rigging plan seven days ahead.

  2. 2
    Anti-vibration packing

    Precision components were removed, crated in timber with dampers and fitted with shock sensors.

  3. 3
    Two shipping waves

    Heavy machines went on 6 flat racks and 4 × 40 ft FCLs, split across two vessels so the schedule never relied on a single sailing.

  4. 4
    Unloading and placement on foundations

    The same crane was mobilised to Makassar. Machines went straight onto their foundations according to the new plant layout.

03

Results

days from the first dismantling to production restart, against a 14-day target
11
machines damaged or needing major recalibration
0
production days saved compared with the client's original estimate
3

Shock sensor data and the signed handover reports are available for review if your procurement team needs them.

Project photos

  • Row of wooden machine crates strapped on a tronton truck bed
    Lifting the 18-tonne machine at the original plant.
  • Packing the precision components.
  • First wave, 6 flat racks.
  • Placement at the destination plant.
PHOTO
“We set aside three days for recalibration. We never needed them. The first line was in production on day eleven.”
Agus Setiawan Plant Manager, PT Contoh Kemasan Nusantara Sample testimonial

Planning a factory relocation? Start with a study, not a price.

Our engineer contacts you within 1 working day to go through your machine list and timeline.

  • All-risk policy per project · Sample
  • Client references available on request
  1. 1 Send your machine listApproximate dimensions and weights are enough.
  2. 2 Talk to an engineerWithin 1 working day, including a survey date.
  3. 3 Receive a technical proposalCost, schedule and method statement.
Request a quote WhatsApp