Case study · Mining · Sea and land

12 mining dump trucks mobilised in 3 weeks

Client
LOGO PT Contoh Tambang Borneo
Service
Project cargo, sea and land
Cargo
12 × 100-tonne dump trucks, partly dismantled
Route
Tanjung Priok → South Kalimantan mine site
Duration
3 weeks · October 2025

Sample case study · data not final

01

Challenge

A mining contractor had to mobilise 12 × 100-tonne dump trucks to a South Kalimantan site before the rainy season closed the mine road.

Every week of delay meant missing that quarter's coal production target.

  • 100-tonne unitsToo wide and heavy for public roads when fully assembled.
  • Weather windowThe mine road closes once the rains set in.
  • ReassemblyHad to be done on site by the manufacturer's technicians.

02

Solution

  1. 1
    Partial dismantling at the port

    Dump bodies and wheels were removed at Tanjung Priok so the units fit the barge.

  2. 2
    Barge direct to the site jetty

    One barge carried 6 units, on two back-to-back sailings with no transhipment.

  3. 3
    Lowbed from jetty to workshop

    Main frames moved by lowbed at times agreed with the mine road operator.

  4. 4
    Reassembly with the manufacturer

    The manufacturer's team reassembled the units while our team supplied cranes and the work area.

03

Results

dump trucks delivered and reassembled on site
12
weeks from port to ready for operation
3
days of slippage on the mobilisation plan
0

The barge schedule, component lists per unit and reassembly reports are available for review.

Project photos

  • Mining dump truck carried on a lowbed trailer
    Six units on one barge.
  • Partial dismantling at the port.
  • Lowbed from jetty to workshop.
  • Reassembly on site.
PHOTO
“The last unit arrived a week before the first rain. Any later and we would have lost a quarter's production.”
Rudi Hasibuan Equipment Manager, PT Contoh Tambang Borneo Sample testimonial

Mobilising heavy equipment to a remote site? Start with a loading plan and barge schedule.

Our engineer contacts you within 1 working day to go through your equipment list and mobilisation timeline.

  • All-risk policy per project · Sample
  • Client references available on request
  1. 1 Send your machine listApproximate dimensions and weights are enough.
  2. 2 Talk to an engineerWithin 1 working day, including a survey date.
  3. 3 Receive a technical proposalCost, schedule and method statement.
Request a quote WhatsApp